Category
Marine Construction
Pier/Wharf Construction
Pile Driving
Client
Maryland Environmental Service
Location
Baltimore Harbor
Baltimore, MD
Key Challenges & Project Details
- Cox Creek dredge disposal area a key interim step in developing the dredge spoil containment areas for Baltimore Harbor’s future dredging requirements
- Project consisted of construction of a bridge and pier to process dredge materials from Baltimore Harbor
- Construction of 100 foot long bridge to connect pier to shore
- Pier and bridge constructed to support large excavation equipment and off road, earth mover trucks
- Construction of workboat fixed pier and floating pier, attached to main pier and bridge
- Details of construction:
- 50’ by 300’ pier with 32’ by 100’ land bridge
- 102 20-inch square concrete piles
- 995 LF cast-in-place concrete caps
- 18,000 SF of pre-stressed concrete planks
- Forming and pouring cast-in-place concrete pier and bridge deck
- 400 LF cast-in-place concrete barrier walls
- 6,700 SF timber crane mats, navigation lights, composite piling/rubber fender system
- 3,500 SF steel sheeting abutment
- 600′ x 16′ permanent gravel access road
- Additional work, not included in original contract, was added by the owner
- Project completed with no recordable or lost time injuries